One hundred years later, Franklin County paid for the contractor’s cost-cutting, as chunks of the tower began raining down upon its citizens. After encircling the top of the building with chicken wire, county officials began the bid process for rebuilding and restoring this historic gem. The problem was finding a company capable of restoring the courthouse so that it retained its historic value and appearance - and so that it remained on the National Registry of Historic Places, a distinction it had held since 1976.
Enter Renaissance Roofing, a specialty roofing company headquartered just outside of Chicago in Belvidere, Ill. The company was founded 15 years ago and completes residential and commercial roofing projects across the country. One of three companies to submit a bid for the Franklin County Courthouse project, Renaissance ultimately won the project based on its national reputation for its slate and tile roofing projects. “Our experience with highly technical and specialty roofing laid the groundwork for the courthouse job,” said Robert W. Raleigh III, Renaissance Roofing’s General Manager and son of the company’s founder. “Once we arrived on site in Iowa, it was clear we had our work cut out for us.”
Originally, the tower was constructed with a post-and-beam skeleton wrapped in terne metal. The metal overlay was attached to the wooden substructure using steel nails, which cut costs for the cash-strapped original contractor, but led to significant weather-related damage over the years. “Because the metal wasn’t water-tight, it caused extensive damage to the framing underneath, which all needed to be replaced,” explained Raleigh. Renaissance contracted with a carpentry firm that eventually replaced 400 linear feet of timber framing - a job that took six months and 6,000 man-hours in structural and finish carpentry work.
Dismantling and salvage alone took four weeks to complete. Aside from the photography, labeling and cataloging, Renaissance also had to contend with 100 years’ worth of Mother Nature. “The pigeons were pretty upset because they had lived in the tower for generations,” Raleigh recalled. “There were literally hundreds of pounds of bird excrement up there.”
Once dismantled, the crew hauled the salvaged metal back to Renaissance’s Belvidere headquarters, where they painstakingly laid out every piece, replicating the project on their shop floor. “Then the real work began,” said Raleigh. “We replaced 100 percent of the original sheet metal, turning out 10,000 square feet of Follansbee Steel’s Terne Coated Stainless Steel Two (TCSII), which was the material the project’s architects specified.” Workers used brake forming, metal stamping and pressing, and metal formed on planishing hammers and an English Wheel to manufacture the new pieces. The team also put in hundreds of hours of hand-hammering parts on a lead shot bag.
“There simply aren’t as many sheet metal craftsmen now as there were in 1890, and their craftsmanship and ingenuity was simply impeccable,” said Raleigh. “My staff learned a lot through this project; we simply don’t have the same type of skills as they did 100 years ago.”
With in-shop fabrication complete, the Renaissance crew returned to Franklin County in November 2005 for on-site installation. Workers had to contend with the extremes of Midwestern weather throughout the installation process, which lasted 13 months, until December 2006. With the base of the tower reaching to 70 feet, and the top of the tower scaling to 125 feet, workers had to deal with sun, cold and wind constantly. “On a calm day, winds were blowing 20 to 30 miles per hour up there,” recalled Raleigh.
In addition to the extremes of weather, crews measured progress on this job in inches per day, not feet. “This type of work requires a high level of patience,” said Raleigh. “It takes a special person to go out there day after day and work but see very little progress.”
On-site installation was completed in December 2006, and crews returned in March 2007 to put the finishing touches on the job, including painting the steel to match the courthouse and using a crane to place the statue that resides at the top of the tower. The results are impressive. “This project cost $1.5 million and took 21 months to complete, but it was worth it,” concluded Raleigh. “It looks great - and it truly now lives up to its designation on the National Register of Historic Places.”
For more information about Renaissance Roofing, call 800-699-5695 or visit www.claytileroof.com .
Sidebar: By the Numbers
• 12,500 man-hours in metal fabrication and installation by Renaissance Roofing.• 10,000 square feet of Follansbee Steel’s Terne Coated Stainless Steel (TSCII) used.
• 6,000 man-hours in structural and finish carpentry work.
• 1,700-plus individually stamped sheet metal ornaments.
• 400-plus linear feet of timber framing replaced.
• 125 feet of elevation to top of tower.
• 70 feet of elevation to base of tower.
• 100-plus pieces of hand-hammered curved parts installed.
• 100-plus pieces of metal custom-formed on an English Wheel.
• 20 different individual molds required for stamped sheet metal components.
• 5 historic copper statues repaired.